Generator Sizing Calculator: From Running Load to a kVA Range

Most sizing arguments are really arguments about assumptions. This calculator puts the assumptions in front of you, converts a running load into a capacity range, and links to the ratings that sit inside that range. It is a first screen for an enquiry, not a substitute for a design.

Diesel generator sets of different ratings arranged in a production workshop
A capacity range narrows the conversation. The load list and the largest motor decide whether the range is right.
Tool principle

A calculator cannot know what your site will do next year, how often the largest motor starts, or what the ambient temperature is. It can only make the arithmetic visible, so that the assumptions can be argued with.

The calculator

Two numbers and two selections are enough to produce a first range: the total running load, the largest motor, how that motor starts, and the phase arrangement. If the site has no single dominant motor, enter zero for the motor and the tool will size on the running load alone.

Design loadNot yet calculatedRequired capacityNot yet calculatedRange to discussEnter a load Planning estimate. Power factor 0.8 and the starting multipliers are rules of thumb, not measurements of your site.

The output is deliberately a range rather than a number. The lower end is the first standard rating that covers the calculated requirement; the upper end is the next rating, which is what you would look at if the load is expected to grow or if the largest motor starts often.

The assumptions, stated plainly

Every sizing figure rests on assumptions, and hiding them is how buyers end up with a set that is wrong in a way nobody can explain. These are the ones this tool uses.

The power factor is taken as 0.8. This is a rule of thumb for planning, not a measurement of your site. A site dominated by motors runs at a different power factor from a site dominated by electronics, and the alternator's actual capability depends on the load it sees.

The starting margin is applied only to the largest motor, not to every motor, because in practice the largest motor is what decides the surge. The multipliers are rules of thumb: a direct-on-line start is treated as the heaviest case, a star-delta start as lighter, a soft starter as lighter still, and a variable speed drive as close to no surge at all.

No allowance is made for altitude, ambient temperature, or the age of the set. No allowance is made for future load. Those belong in the conversation that follows, not in the arithmetic.

The assumptions behind the calculator, and how much weight each one carries
AssumptionValue usedStatus
Power factor0.8Rule of thumb for planning, not a measurement
Surge, direct on lineMultiplier applied to the largest motorRule of thumb, heaviest case
Surge, star-deltaLower multiplier than direct on lineRule of thumb
Surge, soft starterLower againRule of thumb
Surge, variable speed driveTreated as close to no surgeRule of thumb
HeadroomOne standard rating above the minimumA range, not a requirement
Site conditionsNot modelledBelongs in the engineering review

How to read the result

The first line of output is the design load in kW: your running load plus the surge of the largest motor expressed as extra capacity. The second line converts that to kVA at the planning power factor.

The third line is the useful one. It names the first standard rating that covers the requirement and the one above it, and links to both. Those two pages describe the machines in that range; the choice between them is a commercial and operational question rather than an arithmetic one.

If the result lands at the very top of a rating, that is a signal rather than an answer. A load that only just fits a rating will not tolerate a motor starting under full load, a hot afternoon, or a year of growth. The next rating up exists for exactly that case.

The full capacity ladder

The table below lists every rating this site describes, with the output at the planning power factor and the duty each is usually asked to carry. It is here as a static list, so that the ladder can be read without running the calculator above.

Read it as a map rather than a recommendation. The two ratings a site should actually compare are the ones returned by the calculator for its load; the rest of the ladder is context, and the pages behind each rating describe what that size is specified to do.

Every rating described on this site, with output at 0.8 power factor and typical duty
RatingOutput at 0.8 power factorWhat it is typically asked to carry
10 kVA8.0 kWSmall shop, kiosk or single office with a modest load
12 kVA9.6 kWShop with a freezer, small office, house with a managed load
15 kVA12.0 kWShop with refrigeration, an office unit, a house with a managed load
20 kVA16.0 kWShop with refrigeration, guest house, small office suite
25 kVA20.0 kWLarger shop, small guest house, light commercial unit
30 kVA24.0 kWSmall hotel, clinic, workshop with light motors
40 kVA32.0 kWRestaurant, clinic, small factory unit
45 kVA36.0 kWGuest house, small manufacturing unit
50 kVA40.0 kWSmall hotel, school block, light industrial unit
60 kVA48.0 kWHotel floor, cold room, workshop
75 kVA60.0 kWSmall factory, commercial building, hospital block
80 kVA64.0 kWHotel, school, medium workshop
100 kVA80.0 kWFactory unit, commercial building, hospital
125 kVA100.0 kWLarger factory unit, hotel, data room
150 kVA120.0 kWIndustrial unit, hospital, commercial complex
160 kVA128.0 kWIndustrial unit, multi-floor commercial building
165 kVA132.0 kWSame class as 160 kVA, on a different rating basis
200 kVA160.0 kWFactory, mall, data centre, large hotel
250 kVA200.0 kWHeavy industrial unit, multi-building site
300 kVA240.0 kWIndustrial plant, large commercial complex
350 kVA280.0 kWHeavy plant, mining support, large facility
400 kVA320.0 kWHeavy industry, large facility
500 kVA400.0 kWHeavy industry, multi-building site
600 kVA480.0 kWLarge industrial plant
700 kVA560.0 kWLarge industrial plant, mining
800 kVA640.0 kWLarge industrial plant, mining, utility support
1000 kVA800.0 kWLarge industrial or utility-scale site

Three worked examples

The examples below show how the arithmetic behaves at three very different scales. They use the same assumptions as the tool, so the outputs can be reproduced by entering the same numbers.

Three worked examples using the same assumptions as the calculator
CaseInputsDesign loadRequired capacityRange returned
Small single-phase site5 kW running, no dominant motor, single phase5.0 kW6.3 kVA10 kVA to 12 kVA
Three-phase site with one large motor30 kW running, 15 kW motor starting direct on line52.5 kW65.6 kVA75 kVA to 80 kVA
Multi-load industrial site120 kW running, 45 kW motor starting star-delta156.0 kW195.0 kVA200 kVA to 250 kVA

What this calculator cannot answer

It cannot tell you whether your load list is complete. Missing loads are the most common reason a set is undersized, and no arithmetic can recover from an input that was never entered.

It cannot tell you how often the largest motor starts. A motor that starts twice a shift and one that starts every few minutes place different demands on the same set, and the second case needs more margin than the multiplier implies.

It cannot tell you whether the site will grow. A set chosen at the bottom of the range is a set that will be exchanged if the site adds a cold room or a second shift.

It cannot assess the alternator's behaviour on your specific load, the effect of ambient temperature in a confined plant room, or the condition of an existing installation the new set will connect to.

And it cannot price anything. Capacity and cost are related, but the relationship depends on the engine platform, the enclosure and the delivery term, which is why this page does not attempt a figure.

From a range to a quotation

Take the range, pick the rating you want to discuss, and send the load list behind it. A supplier who receives the load list can confirm or challenge the range; a supplier who receives only a kVA figure can only quote it.

The sizing guide covers the method in more depth, and the kW, kVA and kWh page explains the conversion this tool relies on. Where the result sits inside a band rather than at one rating, the band pages are the better next read: 10 to 30kVA, 30 to 100kVA, 100 to 300kVA and 300 to 500kVA.

Once the capacity is settled, the next question is what it will burn. That is a different calculation with a different purpose, and it is covered by the fuel consumption calculator, which works from the set's rated output and your average load factor rather than from a load list.

Questions about the calculation

These are the questions that come up when a buyer compares the tool's output with a quotation they have received. Where the two disagree, the disagreement is usually about an input rather than about the arithmetic.

Send the load list behind the range

Tell us the running load, the largest motor and how it starts, the phase and voltage, and what the site does. We will confirm the range and say if the arithmetic is missing something the site knows.

Get a written quotation

Three fields. We reply with the rating, the engine option and the delivery basis.

Send on WhatsApp

WhatsApp RFQ template

Hello, I used the sizing calculator and it suggested a range. My running load is [kW], the largest motor is [kW] starting [method], and the site is [describe]. Please confirm the size and quote it.

Send this RFQ on WhatsApp

Frequently asked questions

Is this calculator a substitute for a site survey?

No. It is a first screen that turns a load list into a capacity range. A survey covers the things the arithmetic cannot: the actual starting duty, the ambient conditions, the existing installation and the growth plan.

What power factor does it use?

0.8, applied as a planning rule of thumb rather than as a measurement. A site dominated by motors will behave differently from one dominated by electronics.

Why does it give a range instead of one number?

Because the margin between the minimum that covers the load and the next standard rating is a commercial decision about headroom, not an arithmetic result.

Should I enter every motor as the largest motor?

No. Enter the largest single motor, because that is the one whose start decides the surge. Entering several motors multiplies a surge that does not happen simultaneously.

What if my load is above the largest rating in the tool?

The tool stops at the top of the ladder it knows. Above that, the answer is usually a different arrangement, such as multiple sets operating together, and it needs an engineering review rather than a calculator.

Does the result include the changeover or the installation?

No. It is a capacity calculation only. The changeover, cabling, foundation and ventilation are separate scope items with their own requirements.

How does this differ from the fuel consumption calculator?

This one answers how much capacity the site needs. The fuel calculator answers how much the chosen set will burn at a given load. They use different inputs and answer different questions.