In this band, sequence is worth more than capacity. Motors started in a controlled order frequently allow a smaller set than the same motors started together, and the saving is real.
Sequence the loads before buying capacity
Industrial sites rarely need every motor started at once. Compressors, chiller plant, process drives and pumps can usually be brought on in a fixed order, and that order is what the set is actually sized against.
Writing the order down changes the specification in a way that no discount can. It also gives the controller and switchgear scope a clear purpose, because the operating logic has to match the written sequence rather than an assumption.
Where a simultaneous restart genuinely cannot be avoided, state it as a constraint. The correct answer to that constraint is a larger alternator frame and a larger set, and it is much cheaper to say so before the order than after.
Reference configurations 300-500kVA
From the product directory, as a comparison reference. Confirm the final voltage, phase and enclosure against the written quotation.
| Model | Prime rating | Standby rating | Engine options | Example use |
|---|---|---|---|---|
| NGS-300 | 240kW / 300kVA | 264kW / 330kVA | Cummins, Perkins or Weichai | Factory, hospital |
| NGS-350 | 280kW / 350kVA | 308kW / 385kVA | Cummins, Perkins or Weichai | Factory, hospital |
| NGS-400 | 320kW / 400kVA | 352kW / 440kVA | Cummins or Perkins option | Industrial backup |
| NGS-500 | 400kW / 500kVA | 440kW / 550kVA | Cummins, Perkins or Weichai | Estate, plant, project |
A common stopping point in this band is the 400kVA generator price page.
Cooling, ambient and site conditions
A set rated at a reference condition is not automatically rated at the buyer's site. High ambient temperature, restricted ventilation or altitude reduce the usable output, and the cooling package has to be selected for the real installation.
This is why the radiator and ventilation arrangement belongs in the quotation rather than in the installation contractor's scope. Placing an industrial set in a room with an undersized louvre area is a common cause of overheating complaints on otherwise sound machines.
If the set will stand outdoors in a coastal or dusty environment, say so. Enclosure treatment, filtration and maintenance access all change with the environment.
Load testing and protection scope
Agreeing the test arrangement before production is completed is the cheapest form of risk control at this value. Decide what will be tested, at what load, and what evidence will be supplied with the unit.
Alongside the test, settle the protection and control scope: breaker rating, controller functions, alarms, shutdown protection, remote start and any transfer or synchronising communication. These items are easy to assume and expensive to retrofit.
The factory acceptance test guide, the CIF Lagos shipping scope and the pharmaceutical factory guide cover the arrangements that can be written into the order.
Get a written quotation
Three fields. We reply with the rating, the engine option and the delivery basis.
Industrial range questions
What information is needed for a quotation in this band?
The load schedule with a starting sequence, the largest motor and its starter type, which loads can start together, the site ambient and installation position, the enclosure requirement, the protection and control scope and the delivery basis.
Can factory load testing be arranged?
The arrangement can be agreed as part of the order. What matters is deciding before production completes what will be tested, at what load, and which records or photographs will be provided with the unit.
Should the fuel tank be built into the base?
It depends on the runtime required and the refuelling plan. Base tanks simplify installation but limit autonomy, while larger external storage needs its own handling and safety arrangements, and the choice belongs in the written scope.