Beyond 500kVA, asking which single set to buy is often the wrong first question. The right first question is whether one set, several parallel sets, or a staged arrangement best fits the load and the outage risk.
When a single set stops being the answer
Two smaller sets running in parallel can offer redundancy that one large set cannot, since losing one unit leaves partial capacity rather than nothing. They also allow the plant to run one set lightly during low demand and bring the second online for peaks.
The trade is complexity. Parallel operation requires matching controls, synchronising equipment and a protection philosophy that is designed as a system, and that work has to be planned from the beginning rather than added later.
For a site with a staged build, a parallel arrangement also lets capacity arrive with demand instead of being bought upfront and left idle.
The lower end of the industrial range is a different decision from this one and is covered in industrial generator selection.
Reference configurations 500-2000kVA
From the product directory, as a project reference point. Enclosure and container arrangements are confirmed per project in the written quotation.
| Model | Prime rating | Standby rating | Engine options | Enclosure | Example use |
|---|---|---|---|---|---|
| NGS-500 | 400kW / 500kVA | 440kW / 550kVA | Cummins, Perkins or Weichai | Silent or container | Industrial backup |
| NGS-650 | 520kW / 650kVA | 572kW / 715kVA | Cummins or Perkins option | Silent or container | Factory, plant |
| NGS-800 | 640kW / 800kVA | 704kW / 880kVA | Cummins or Perkins option | Silent or container | Hospital, data facility |
| NGS-1000 | 800kW / 1000kVA | 880kW / 1100kVA | Cummins or Perkins option | Container optional | Large industrial site |
| NGS-1500 | 1200kW / 1500kVA | 1320kW / 1650kVA | Cummins, MTU or Baudouin option | Container optional | Factory, oil and gas |
| NGS-2000 | 1600kW / 2000kVA | 1760kW / 2200kVA | MTU or Cummins option | Container type | Large project power |
The table shows our standard build bands. Between them we also supply 600 kVA and 700 kVA sets, and a 650 kVA unit in the same frame family. Above 1000 kVA, 1500 kVA and 2000 kVA are project builds: the configuration is fixed after the site load study, so they are quoted against a specification rather than off a catalogue page.
Containerised sets and parallel operation
Containerised arrangements suit remote sites, harsh environments and projects where the power plant has to be relocated. They also simplify shipping, because the machine travels in a structure that is already designed for handling.
The trade is in maintenance access and ventilation. A container has to be laid out so filters, belts, hoses and control panels remain reachable, and so that the cooling air path is not compromised by the container itself.
Where parallel operation is planned, confirm whether the container solution includes the synchronising and load-sharing equipment or whether that sits in separate switchgear. The boundary between the two scopes is where projects most often develop gaps.
Containerized builds in this range are worked through in planning a containerized 500-2000kVA set.
Shipping, lifting and site handling
Large units need the shipping plan settled early, because dimensions, gross weight, centre of gravity, lifting points and the destination handling method all interact. A plan that works in a factory yard may not work at a congested site access road.
Fuel planning belongs here too. Large sets consume substantial volumes per day, so external storage, transfer pumps, day tanks and monitoring arrangements become part of the design rather than accessories.
The CIF Lagos shipping scope, the data centre power guide and the telecom tower power guide describe the arrangements that can be defined before production.
Get a written quotation
Three fields. We reply with the rating, the engine option and the delivery basis.
Heavy project questions
When should a project use parallel generators instead of one large set?
When redundancy, staged expansion or load flexibility matters more than simplicity. Two sets in parallel can keep partial capacity running after the loss of one unit, which a single set cannot do.
Can sets in this band be containerised?
Yes, and container arrangements suit remote or harsh sites and simplify shipping. The layout still has to preserve maintenance access and the cooling air path, and the synchronising equipment boundary has to be defined.
What shipping information has to be settled early?
Dimensions, gross weight, centre of gravity, lifting points, the packing arrangement and the destination handling method. These cannot be adjusted after production, and a plan that works in the factory may not work at the site entrance.