A generator can charge a battery bank, and on many sites it should. Whether it does so efficiently depends on two numbers that are easy to compute and easy to get wrong: the charger current and the generator's loading band.

Short answer

Work out the charger's DC power as battery volts times charge amps, divide by charger efficiency and power factor to get the AC demand, then add the site load. A 48V bank taking 40A is about 1.9kW of DC and about 2.25kVA of AC, which is small beside a site load and large beside nothing.

The efficiency chain, litre by litre

Every conversion between diesel and a delivered kilowatt-hour loses something, and the losses stack. Following one litre through the whole chain is the clearest way to see why charging a battery is not free energy storage, and why a set that charges a bank for hours can burn more fuel than the load it is covering would have used directly.

Start with the fuel. A litre of diesel carries roughly 9.9kWh of thermal energy. A well-loaded engine converts a little over a third of that into rotation at the flywheel, and the alternator converts most of the rotation into electricity. The working figure at the terminals for a properly loaded set is about 3.9kWh per litre, which corresponds to roughly a quarter of a litre for each kilowatt-hour produced. That figure is the same one used in the fuel consumption guide, and it improves at high load and worsens sharply at low load.

After the terminals the losses belong to the charging system rather than the generator. A charger converts alternating current to the direct current the battery needs, and a realistic efficiency for that stage is ninety percent. The battery then has its own round-trip loss: energy put in is not all available on the way out. Lead-acid typically returns about eighty-five percent of what it absorbs, so a kilowatt-hour stored costs more than a kilowatt-hour delivered.

What remains of one litre of diesel after each conversion stage, using 3.9kWh at the terminals, a 90 percent charger and an 85 percent battery round trip
StageEfficiency appliedkWh remaining
Fuel energy to alternator terminalsWorking figure for a loaded set3.90
Charger, AC to DC90 percent3.51
Battery, in and back out85 percent2.98
Delivered to the loadAbout 30 percent of the fuel energy2.98

The arithmetic gives about a third of a litre for every kilowatt-hour that eventually reaches the load through the battery, against roughly a quarter of a litre for a kilowatt-hour delivered straight from the alternator. That difference is the price of storing energy, and it is the number to carry into any comparison with running the load directly. A site that charges a battery to run a load it could have run at the time is paying that difference for no benefit.

Charger output against set capacity

Charging current is quoted on the direct-current side, so the first step is to convert it into the alternating-current demand the generator actually supplies. Two relationships do the whole job, and both are worth writing down because they are the ones that get confused.

DC power = battery volts × charge amps

A 48V bank taking 40A absorbs 48 × 40 = 1,920W, or 1.92kW.

AC demand = DC power ÷ (charger efficiency × power factor)

At 90 percent efficiency and a power factor of 0.95: 1,920 ÷ (0.90 × 0.95) = 2,246VA, which is about 2.25kVA. For reference, the current that represents on a three-phase supply follows the same rule used in the kVA to amps chart: kVA × 1000 ÷ (1.732 × voltage).

The table below runs those two relationships across the bank sizes that appear most often, using a 48V nominal bank. The current column is the charge rate expressed as a multiple of capacity in amp-hours, which is how charger settings and battery datasheets are written.

Charge current against bank capacity at 48V, with the DC power absorbed and the AC demand on the generator at 90 percent efficiency and 0.95 power factor
BankCharge rateCharge currentDC powerAC demand
100Ah0.10 of capacity10A0.48kW0.56kVA
200Ah0.10 of capacity20A0.96kW1.12kVA
200Ah0.20 of capacity40A1.92kW2.25kVA
400Ah0.10 of capacity40A1.92kW2.25kVA
400Ah0.20 of capacity80A3.84kW4.49kVA
600Ah0.15 of capacity90A4.32kW5.05kVA
800Ah0.20 of capacity160A7.68kW8.98kVA

Two things stand out. The first is that even a large bank at a brisk charge rate draws less than ten kilovolt-amperes, so charging is rarely the reason a site needs a big generator. The second is that the AC demand is larger than the DC figure by a fifth or so, which is the part people forget when they match a charger to a set on paper.

What matters more than the absolute size is the ratio to the set. A charger drawing 2.25kVA from a 30kVA set adds almost nothing to its load and will barely register on the fuel bill. The same charger on a 5kVA set is a substantial part of the rating and has to be sequenced with everything else. Charging is efficient when it makes a lightly loaded set work harder, and inefficient when it pushes a small set to its limit for hours.

Charging while carrying load

Sites rarely charge in isolation. The generator is running for something else, and the charger is a second load added to it. The design question is therefore not the charger alone but the sum, and whether that sum sits in a band where the set runs well.

Take a site with a 5kW load at a power factor of 0.8, which is 6.25kVA, and a 48V bank charging at 100A, which is 4.8kW of DC and about 5.6kVA of AC. Together that is roughly 11.9kVA, so a set in the region of fifteen to twenty kilovolt-amperes carries it at a comfortable loading rather than at its ceiling. A set of ten kilovolt-amperes would be at its limit before the site load grew at all, and the first additional appliance would push it into overload.

The band matters because of how diesel engines behave at light load. A set run at a small fraction of its rating burns fuel mostly to keep itself turning, so each kilowatt-hour delivered costs more than it would at a higher load; the mechanism is set out in the guide to under-loading damage. Charging is one of the few loads that can usefully fill that band, because it can be scheduled rather than following demand. A site whose daytime load is light can charge during the day and switch the charger off at night, turning a wasteful idle period into useful work.

The sequencing matters as much as the arithmetic. Start the generator, let it reach rated speed and stabilise, then enable the charger; a charger that comes on with the set still accelerating applies its load at the worst moment. When stopping, disable the charger first so the set is not left carrying a step-down while the engine cools. On a set with a changeover panel, the charger input should be on the generator side of the changeover so it can only run when the generator is running, which also prevents it from draining a dead supply.

Lead-acid and lithium accept differently

Batteries do not accept current on demand. Each chemistry has a rate it will take without damage, and that rate sets the practical ceiling on how fast a generator can recharge a bank.

Flooded lead-acid and the sealed variants based on the same chemistry generally accept a charge current around a tenth of their capacity in amp-hours, with a higher rate acceptable in the early part of the cycle. A 400Ah bank therefore charges at roughly 40A, and the last part of the charge is slow by nature: the battery moves into an absorption phase where voltage is held and current tapers, and that phase can take as long as the bulk phase did. This is why a bank that is ninety percent charged still occupies the generator for another hour or more. Charging faster than the manufacturer allows shortens life through grid corrosion and heat, and it will not actually fill the battery sooner.

Lithium iron phosphate accepts a much higher rate, commonly a third to a half of capacity, so the same 400Ah bank can take 130A to 200A if the charger and the battery management system both allow it. The round-trip efficiency is also better, in the region of ninety-five percent rather than eighty-five, which improves every number in the chain above. The constraints move elsewhere: the battery management system can refuse current without warning, charging at low temperature is limited, and sustained high ambient heat shortens life regardless of how gently the bank is cycled.

Two practical consequences follow for a Nigerian site. First, a lithium bank can absorb a generator's output quickly, so charging time is shorter and the generator runs fewer hours at a useful load; the fuel saving is real but it comes from the hours, not from the conversion. Second, a lead-acid bank needs a longer, lower-current charge and suits a site that runs its set for several hours anyway. Matching the chemistry to the generator's duty is at least as important as matching the current.

Sizing from your own daily consumption

The usable method starts from the energy the site actually needs overnight, not from the charger's label. Take a site that needs nine kilowatt-hours between sunset and morning: lighting, fans, a fridge and a television. That figure is the delivered energy, so the energy that has to be put back into the battery is larger by the round-trip loss.

Energy to replace = delivered kWh ÷ battery round-trip efficiency

Nine delivered kilowatt-hours at eighty-five percent round trip needs 9 ÷ 0.85 = 10.6kWh put into the battery.

Next, divide by the charger's DC power to get the hours. At 48V and 40A the charger delivers 1.92kW, so 10.6 ÷ 1.92 = 5.5 hours of charging. During those hours the set carries the charger at about 2.25kVA plus whatever the site is using at the time; if the daytime load is 3kW at a power factor of 0.8, that is another 3.75kVA, so the set is working at roughly six kilovolt-amperes.

Now compare that with the set's rating. A set rated ten kilovolt-amperes would be at about sixty percent of its rating during the charge, which is a good place to be. A set rated twenty-five would be at a quarter load, which is the band where fuel per kilowatt-hour rises sharply and where the engine runs cold. In that case the honest options are to charge at a higher current if the battery allows, to move more of the site load into the charging window, or to accept that the set is larger than this duty needs.

The same arithmetic run backwards tells you whether the bank is big enough. If the overnight need is nine kilowatt-hours and the bank is lead-acid, it must be sized so that nine kilowatt-hours is no more than about half its nominal capacity, because deep daily discharge shortens life. A 48V 400Ah bank holds 19.2kWh nominal, so nine kilowatt-hours is a little under half and the bank is about right. A 200Ah bank would be discharged close to its limit every night and would not last. The solar and generator hybrid sizing guide takes the same method further when photovoltaic input shares the charging duty.

Wiring order and protection

The order in which the pieces are connected decides whether the system is safe as well as whether it works. The battery bank comes first, with a fuse or breaker on the positive cable as close to the terminals as possible, because a short on a large bank is a fire rather than a fault. Then the charger and inverter connect to that protected point, each through its own isolation so that either can be worked on without the other.

On the alternating-current side, the generator feeds the charger input through a breaker sized for the charger's AC current, and the charger's output to the site goes to a separate distribution board rather than back into the generator feed. A charger whose AC input and AC output are looped together will try to supply itself, which is a fault that appears only when the generator stops and the inverter keeps the circuit alive.

Earthing deserves its own decision. The generator's neutral and earth relationship, and whether the inverter bonds neutral to earth when it is running on battery, have to be settled together; a system that bonds in two places at once will trip residual-current protection intermittently and mysteriously. The earthing and grounding guide covers the generator side, and the inverter manual governs its own. Where a changeover panel sits between the two sources, the ATS panel guide explains what the panel does and does not switch.

Two settings are worth commissioning properly rather than leaving at their defaults. The charger's maximum current should be set to what the battery actually accepts, not to the charger's capacity, so a small bank is not cooked by a large charger. The inverter's AC input limit should be set so that the charger reduces its draw when the site load rises, rather than adding to it until the generator trips. Both are menu settings on most inverter chargers and both are routinely left untouched.

One further check belongs here because it interacts with the rest of the site: the charger expects a particular frequency and voltage, and a set that is drifting will make it derate or refuse. If the equipment came from a 60Hz market, the guide to 60Hz appliances on 50Hz generators explains what that does to a charger's behaviour.

When to run the load directly

Batteries are for moving energy in time, not for converting it. If the load is present while the generator is running, sending the power straight to the load avoids the charging and discharging losses entirely, and that is roughly a quarter more kilowatt-hours from the same litre. The case for the battery is the hours when the generator is off.

That gives a simple decision rule. Loads that coincide with generator running hours should run from the generator. Loads that must run when the generator is off belong on the battery. A site that charges all day to run air conditioning all evening is using the battery as a very expensive way to shift a load it could have carried directly, and it pays the round-trip loss for the privilege.

The arrangement that works well on most Nigerian sites is a split rather than a choice: the generator carries the heavy and intermittent loads, the battery carries the small steady overnight base, and the charger runs only during hours when the generator is already working. That keeps the set in an efficient band, keeps the battery within its depth of discharge, and produces the lowest fuel per delivered kilowatt-hour of the options discussed here. The generator versus inverter running cost comparison sets out the same conclusion from the cost side, and the daily running hours guide shows how to establish the hours figure that the whole calculation depends on.

Where the site is choosing a generator for this duty rather than adapting one it already has, the charging load should be stated in the enquiry along with the site load and the hours available. A set sized on the site load alone will be at a poor loading band for most of its life, and the generator range should be discussed with both figures on the table.

Charging and capacity questions

Can a generator charge an inverter battery directly?

Yes, through the inverter charger or a separate battery charger. The generator supplies alternating current to the charger, the charger converts it to the direct current the battery needs, and the battery supplies the inverter. The generator never connects to the battery terminals directly.

How many amps should I charge a 48V battery bank at?

Lead-acid generally accepts about a tenth of its capacity in amp-hours, so a 400Ah bank takes roughly 40A. Lithium iron phosphate commonly accepts a third to a half, so the same bank can take 130A to 200A if the charger and battery management system allow it.

How much load does charging add to the generator?

Multiply battery volts by charge amps to get DC power, then divide by charger efficiency and power factor. A 48V bank at 40A is 1.92kW of DC and about 2.25kVA of AC, which is a modest addition to a large set and a significant one to a small set.

Is it cheaper to charge a battery or run the load directly?

Running the load directly uses roughly a quarter of a litre per kilowatt-hour, while the same energy through a battery takes about a third of a litre because of charger and battery losses. Charging only makes sense for loads that must run when the generator is off.

Why does my charger stop charging before the battery is full?

Most likely the inverter's AC input limit is reducing charger current as the site load rises, or the battery has reached its absorption phase where current tapers by design. Check both settings before assuming a fault.

Can I charge while the generator is also carrying the site?

Yes, and it is usually the better arrangement, because the set then runs at a healthier load. Add the site load in kVA to the charger's AC demand and check the total against the rating rather than against the charger alone.