Marine and boat power

Marine Diesel Generator for Boats and Crew Vessels in Nigeria

A set that lives on a hull is specified by the hatch it must pass, the angle it must survive and the water it must cool with. This page sets out the four constraints that decide a marine build, and works one crew boat load board through to a rating.

Buyer answer

A marine set is chosen by three numbers before the rating is discussed: the largest opening it must pass, the maximum angle the hull will hold, and the largest motor that starts while the rest of the board is live. On a typical crew boat the running load is around 40 kW but the bow thruster presents a starting step above 110 kVA, and that step sets the alternator. Cooling choice follows the water: raw water where it is clean, keel cooling where silt would block a strainer.

What makes a marine set different from a land set

A generator that lives on a boat is asked to do three things a yard set never is. It has to survive an atmosphere that corrodes bare steel in weeks, it has to keep working while the floor under it is tilted, and it has to be serviceable through a hatch rather than from a walk-around platform. Those three constraints reorder the specification, and they are the reason a marine unit is not simply a canopied set with a different paint finish.

The electrical duty is often smaller than buyers expect. A crew boat or a river barge typically carries navigation electronics, cabin air conditioning, a fresh water pump, deck lighting and a winch, and the continuous load is modest. What decides the rating is not that total but the largest motor starting while the rest of the board is live, and on a boat that motor is usually a bow thruster or a deck winch rather than a pump.

Where the set sits matters as much as what it is. An engine room under a working deck has limited combustion air, limited rejection air and no easy route for a hot exhaust, so the installation detail that is a comfort on land becomes a hard limit afloat. The general principles are in generator cooling system design, but the marine arrangement tightens every margin in that page.

Engine room fit: dimensions, access and service space

Start with the hatch, not with the rating. A set that fits the room but cannot pass the hatch, or cannot be slid sideways past a fuel tank, is a set that will be installed once and never removed without cutting steel. Measure the smallest opening on the route from quay to final position, then compare it with the skid dimensions plus any lifting frame.

Service access is the second measurement. An engine needs its rocker cover lifted, its oil drained, its filters reached and its heat exchanger tube stack withdrawn. On land those are done from three sides; in a hull they are often done from one, at an angle, by one person. If the specification does not state which side each service point faces, the fit will be decided on the drawing and discovered on the water.

Air is the third. A marine set draws combustion air from the same room it heats, so the room needs an inlet sized for combustion plus cooling, and an outlet that does not simply recirculate into the inlet. A common failure on converted hulls is an inlet louvre fitted because it looked adequate, with no calculation behind it, and the set derating itself within an hour of load. The relationship between room airflow and delivered output is set out in generator room ventilation.

Cooling on a boat: raw water, keel cooling and heat exchanger

There are three ways to reject heat from a marine set, and the choice is made by the water the boat works in rather than by preference. A raw water system draws sea or river water through a strainer, passes it through the heat exchanger and discharges it overboard with the exhaust. It is compact and effective, and it is the system most exposed to weed, sand and debris.

A keel cooling system keeps the closed circuit inside the hull and rejects heat through a tank or pipe array on the hull bottom. It removes the strainer from the critical path, which matters on silty rivers and in shallow creeks, and it adds hull work and a permanent appendage below the waterline. A heat exchanger system with a dedicated seawater pump sits between the two and is the usual choice where the set has to be replaceable without dry docking.

Whichever is chosen, the specification should state the raw water flow, the maximum inlet temperature assumed and the strainer size. Those three numbers are what a maintenance crew needs when the set starts to run hot in the second season, and they are routinely missing from quotations that list only the rating and the enclosure.

Tilt, trim and the lubrication question

An engine lubricates by pumping oil to the top of the block and letting it drain back to a sump. Tilt the sump and the oil pools at one end, the pickup can uncover, and the bearings are running on whatever reaches them. Marine installations therefore specify a maximum continuous angle and a maximum intermittent angle, and the sump, pickup and breather arrangement is configured for that envelope rather than for level ground.

In practice two numbers need agreeing before the order: the angle the hull sits at when loaded and underway, and the angle it reaches when a load is lifted over the side. A set rated for a level installation and fitted to a hull that trims hard will not fail immediately, which is what makes the mistake expensive: it degrades quietly over a season and shows up as a bearing or a turbocharger rather than as an obvious installation fault.

Fuel and coolant behave the same way. A tank pick-up that sits at the centre of a level tank will draw air at a sustained angle, and a coolant header tank positioned for a level engine will not be the highest point once the hull trims. Both are cheap to correct at build and awkward to correct afterwards.

Corrosion: what salt does to a set that sits on water

Salt does not attack the paint first; it attacks every fastener, terminal and unpainted machined face, and it does so from the inside of a canopy as readily as from the outside. A set installed on a saltwater hull should be specified with the enclosure finish, the fastener material and the terminal treatment stated, because those are the items that decide whether the unit is still serviceable in year three.

The exhaust is the second front. A wet exhaust mixes cooling water into the gas stream, which keeps the pipe cool and quiet and puts salt water within reach of any point where the mixture can run backwards. The riser height and the injection point are the two details that prevent water reaching the turbocharger when the engine stops, and they belong in the installation drawing rather than in a fitter's judgement at the quay.

Electrical enclosures deserve the same treatment. A control panel that is adequate in a dry plant room will corrode its terminals in a humid engine room, and the failure presents as an intermittent alarm rather than as a clean break. Specifying the ingress protection and the terminal plating at the quotation stage is cheaper than replacing a controller later; the general checks are covered in earthing and grounding practice.

Electrical: earthing, isolation and shore power changeover

A boat has two sources of power and they must never meet. Shore supply and the generator have to be separated by an interlocked changeover, and the earth arrangement has to be decided deliberately: a hull-bonded system and an isolated system are both defensible, but a system that is accidentally one and intended to be the other is a shock risk and a galvanic corrosion risk at the same time.

Where the boat also has an inverter or a battery bank, the neutral arrangement becomes the question that decides whether an earth-leakage device will trip correctly. This is the point at which a marine electrician and a generator supplier need to agree on one drawing; the generator side of that conversation is the same one described in ATS panel selection, with the added constraint that the changeover must break both sources positively rather than rely on a contactor that can weld.

Shore power also varies. Voltage at a Nigerian jetty is not the voltage at the end of a long quay run, and a set configured for one value will be asked to work at another. Stating the actual site voltage, and whether the boat is 50Hz or 60Hz, prevents the most common commissioning surprise on a converted hull.

Sizing a marine set: a worked load table

The table below is a representative crew boat board rather than a real vessel. It is built the same way any marine board should be: convert each load to running kVA at its power factor, apply the starting multiple to the motor that starts last and worst, and check the peak rather than the total.

Representative marine load board: running kW, starting multiple and starting kVA at a power factor of 0.8
LoadRunning kWRunning kVA at 0.8Starting multipleStarting kVA
Bow thruster1518.756112.5
Deck winch1113.75682.5
Air conditioning compressor7.59.375546.9
Fresh water pump2.22.75616.5
Navigation and communications1.51.87511.9
Lighting and galley33.7513.8
Total40.250.25–112.5 peak

Read the last row carefully. The running total is 40.2 kW, which is 50.25 kVA at a power factor of 0.8, and a set chosen on that figure alone would be a fraction of what the board actually demands. The governing number is the 112.5 kVA step from the bow thruster starting with everything else already running, and on a boat that number is usually set by the thruster rather than by the accommodation load.

Two corrections then apply. The set must be rated for the ambient in the engine room rather than for a test cell, which is the mechanism described in high-temperature derating. And the starting multiple should be taken from the motor or thruster data rather than from a default, because a thruster with a soft-start controller presents a very different step from one switched direct-on-line. The general method for building this sum is in the generator sizing guide, and the motor side is set out in three-phase motor and generator sizing.

What to put in the enquiry

A marine enquiry that arrives with six items gets a usable answer: the hull or vessel type, the site voltage and frequency, the largest motor or thruster with its starting method, the maximum continuous and intermittent angles, the raw water conditions including silt, and the route the set must pass through to reach the engine room. Every one of those changes the build rather than the price list.

Delivery is the last item and the one most often left to the end. A set shipped as deck cargo and a set shipped inside a container are packed differently, and the lifting points that suit one are not the points a crane driver will find on the other. The packing and loading sequence is described in generator container loading, and the import terms in CIF Lagos shipping.

Finally, if the engine is a Cummins or a Perkins, the identity of the engine is worth establishing before anything is built around it. The checks are set out in genuine Cummins and Perkins verification, and the same discipline applies to a marine set as to a land one. A unit that has to be lifted out of a hull is an expensive place to discover that the engine is not what the quotation said.

For sets that are moved between hulls, moorings or sites rather than fixed, the mounting and towing questions are covered in trailer-mounted generator sets. The full range of ratings and configurations is listed on the products page.

Get a written quotation

Three fields. We reply with the rating, the engine option and the delivery basis.

Send on WhatsApp

Marine generator FAQ

Can a land generator be used on a boat?

It can be installed, but three things must change: the sump and oil pickup for the angle the hull holds, the cooling circuit for raw water or keel cooling, and the finish and terminal treatment for salt air. A set fitted without those changes will run, and will degrade in a way that is easy to miss until a bearing or a turbocharger fails.

Why does a bow thruster decide the generator size?

Because it starts with the rest of the board already live. A thruster of 15 kW draws about 18.75 kVA running at a power factor of 0.8, but at six times starting current it presents about 112.5 kVA for the duration of the start. That step is usually larger than the total running load of the accommodation.

Is raw water cooling suitable for river work?

It is suitable where the water is clean enough that the strainer can keep up. On silty rivers and in shallow creeks the strainer becomes the critical item, and keel cooling or a closed circuit with a heat exchanger removes that exposure at the cost of hull work or a seawater pump.

What angle can a marine generator run at?

The figure is set by the engine and the sump arrangement, so it must come from the engine data rather than from a general rule. What matters in the enquiry is stating both the sustained angle when loaded and the greater angle reached when a load is lifted over the side.

How is a marine set earthed?

Either a hull-bonded system or an isolated system can be correct, but the choice has to be deliberate and consistent with the changeover and any earth-leakage device. The fault to avoid is a boat that is accidentally half of each, which is both a shock risk and a galvanic corrosion path.

What should a marine generator enquiry include?

Vessel type, site voltage and frequency, the largest motor or thruster with its starting method, the maximum continuous and intermittent angles, raw water conditions, and the smallest opening on the route to the engine room. Delivery as deck cargo or in a container should also be stated, because it changes the packing.